LTE DAU User Guide Issue Date 2017-03-03 HUAWEI TECHNOLOGIES CO., LTD.
Page 2
Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
LTE DAU User Guide About This Document About This Document Overview This document describes the hardware, functions, installation, configuration, operation and maintenance (OM) of the eA680-950 customer premises equipment (DAU). Product Version Product Name Product Version eA680-950 V100R001C00 Intended Audience This document is intended for: ...
The eA680-950 is specially designed for outdoor deployment to obtain better wireless access performance to the LTE network. The eA680-950 can be deployed in wISP, industrial, public security and enterprise network if the performance is acceptable to the network operator.
Page 8
1 Overview Figure 1-3 The eA680-950 connected to a video camera. Use a network cable to connect the eA680-950 to an external device. If the eA680-950 connects to a single device, connect the power adapter directly to the eA680-950. If the eA680-950 connects to multiple devices, connect the power adapter to a Hub or switch and then to the eA680-950, as shown in Figure 1-4.
Storage environment should be equipped with temperature and humidity equipments and dehumidification equipment to monitor and adjust the temperature and humidity. 1.4 Antenna Specifications Table 1-2 and lists the eA680-950 antenna's specifications. Table 1-2 eA680-950 LTE antenna specifications Item eA680-950...
Application security includes wireless security and OM security. 1.6.1 Network Security eA680-950 network security uses Secure Sockets Layer (SSL) and Hypertext Transfer Protocol Secure (HTTPS). The SSL protocol is a security connection technology for the server and client. It provides a confidential, trusted, and identity-authenticating connection to two application layers.
SSL data can reach the destination intact. HTTPS For the eA680-950, the OM TCP applications can use SSL. HTTP over SSL is generally called HTTPS. HTTPS is used for connections between the NMS/WebUI and eA380. SSL also uses the digital certificate mechanism.
In normal cases, the USB port works in slave mode. In slave mode, the USB port will be mapped to a computer UI after the Huawei-provided chip driver is installed on the computer. This UI is locked by default. You can run other AT commands and write data to the SoftSim card only after running the unlock command.
USB ports. If the softsim tool is provided by Huawei, please apply the license of the tool from Huawei, and notice the usage scope. For details of apply guide,see SoftSim Tool License Operation Guide.
About This Chapter This section describes the hardware and cables of the eA680-950. 2.1 eA680-950 Hardware This section describes the appearance, ports, and indicators of the eA680-950. Appearance Figure 2-1 shows the appearance of the eA680-950. Figure 2-1 Appearance of eA680-950s...
Page 20
LTE DAU User Guide 2 Hardware Panel The panel of the eA680-950 provides the Power over Ethernet (PoE) port, SIM card maintenance window, and indicator. Figure 2-2 shows the panel of the eA680-950. Figure 2-2 Panel of the eA680-950 Table 2-1 lists the ports of the eA680-950.
Page 21
Only supports dual-polarized antenna or dual antenna installation. Indicators of the eA680-950 are below the SIM card maintenance window and are used to indicate the running status of the eA680-950. The four indicators from top to bottom are POWER, WLINK, RSSI, and HEAT, as shown in Figure 2-3.
2.2.1 PoE Network Cable The power over ethernet (PoE) network cable is a shielded network cable that is used to connect the PoE port of the eA680-950. The PoE network cable connects to an RJ45 connector at both ends. Background Information The PoE network cable transmits data signals to the eA680-950 and provides DC power for the equipment.
User Guide 2 Hardware 2.2.2 Ground Cable The ground cable ensures the proper grounding of the eA680-950. Appearance The ground cable provides a 6 mm² cross-section, is yellow-green, and has OT terminals at both ends. Figure 2-4 shows the appearance of the ground cable.
Requirements for Site Selection To ensure long-term reliability of an eA680-950, select a site based on the network plan and technical requirements of the equipment, as well as considerations such as hydrology, geology, and transportation.
Requirements for Operating Environment For details about operating environment requirements, see1.3 Hardware Specifications 3.2 Installation Preparation Before you install the eA680-950, unpack and inspect the equipment delivered to the site and prepare the related tools. Prerequisites Perform the following operations to inspect the goods delivered to the site: Unpack the equipment, count the total number of items based on the packing list attached to each packing case, and check whether each packing case is intact.
Page 26
Ensure that there are no obstacles facing the DAU, and enable the DAU to face the base station. Installation Tools Table 3-1 lists the tools used for installing the eA680-950. Table 3-1 Installation tools Hammer drill ESD gloves Vacuum cleaner...
3.3.1 Mounting on a Utility Pole Context Figure 3-2 shows the flowchart for mounting the eA680-950 on a utility pole without an angle adjusting component. Figure 3-2 Flowchart for mounting the eA680-950 on a utility pole without an angle adjusting...
Page 28
LTE DAU User Guide 3 Installation Procedure Step 1 Open the SIM card maintenance window of the eA680-950 and insert the SIM card, as shown in Figure 3-3. Figure 3-3 Installing the SIM card Figure 3-4 shows the correct installation method.
Page 30
If the hose clamp is too long, cut off the extra part. Apply anti-rust oil to the cut in case it gets rusty. Step 4 Fix the eA680-950 on the wall-mounting frame through the dovetail groove, as shown in Figure 3-7.
User Guide 3 Installation ----End 3.3.3 Cable Connection This section describes the procedure for connecting the eA680-950 cables. Procedure Step 1 Connect the ground cable, as shown in Figure 3-17. Figure 3-17 Connecting the ground cable Tighten the ground screws and apply antirust paint to it.
The eA680-950 hardware has been installed. Procedure Step 1 Check whether the eA680-950 hardware is correctly installed. When performing the hardware check for the eA680-950, check the items listed in Table 3-2 in order. Table 3-2 Hardware installation check of the eA680-950...
Page 41
When checking the cable connections of the eA680-950, check the items listed in Table 3-3 in order. Table 3-3 Cable connection check of the eA680-950 Check Item No cable is short-circuited or inversely connected.
Page 42
When the eA680-950 powers on, the RSSI indicator is steady on or blinks. If the RSSI indicator is off when the eA680-950 powers on, the signal strength is too weak. Check the power supply and the angle of the angle adjusting component. For details about the indicator status, see 2.1 eA680-950 Hardware.
The installation of the eA680-950 is complete. The eA680-950 starts correctly based on default parameters during power-on. Procedure Step 1 Start the IE browser, enter http://192.168.1.1 in the address bar, and press Enter. Connect the eA680-950 from the near end using the Web management page.
This section describes the maintenance preparation and fault diagnosis methods for the eA680-950. 5.1 Maintenance Preparation Before performing site maintenance for the eA680-950, learn about the sit information, select required maintenance items, and prepare related tools. Learning About the Site Information Gather the following site information before going to the eA680-950 site to perform maintenance.
Page 45
The computer has been connected to the eA680-950. The installation of the eA680-950 is complete. The eA680-950 starts appropriately based on default parameters after power-on. Procedure When the LTE CPE fails to access the Internet, run the Ping function to quickly check the network connection status.
6 FAQ 6.1 What Do I Do If the Web UI Fails to Be Opened? Problem Description: I cannot visit theWeb management page of eA680-950 through browser. Solution: Step 1 Check wheather the DAU is powered on. Step 2 Check wheather the cables are not properly connected.
LTE DAU User Guide 9 Acronyms and Abbreviations Acronyms and Abbreviations This section lists the acronyms and abbreviations related to the eA680-950. Table 9-1 List of acronyms and abbreviations Acronym/Abbreviation Full Name 3GPP 3rd Generation Partnership Project Address Resolution Protocol...